Project Management

Friday, June 1, 2012

TASK DEPENDENCIES: FS / SS / FF / SF IN MS PROJECT PROFESSIONAL


Task Dependencies : To Define the Relationships Between Tasks 


Predecessor :
A predecessor is a task whose start or finish date determines the start or finish date of its successor task.

Successor : 
A successor is a task whose start or finish date is driven by its predecessor task.

The nature of the relationship between a predecessor task and a successor task determines the type of task dependency to use. We can use FOUR types of task dependencies.

  1. Finish - To  - Start    [ FS ]
  2. Start   - To  - Start    [ SS ]
  3. Finish - To  - Finish  [ FF ]
  4. Start   - To -  Finish  [ SF ]
For Example, if we have Two tasks, Task 1 and Task 2 in our Testing Project , we can define all the 4 relationships by following steps:

  • If Task 2 is having Predecessor as Task 1, double Click on Task 2 
  • Task Information window will appear
  • In the Predecessor section, select the option from Type Drop down list ( FS / SS / FF / SF)
  • Ok

A. Finish - to  - Start Dependency

Task 1 must finish before Task 2 can start. This is the By Default  Dependency created and very commonly used Relationship in Project.



 B. Start - to  - Start Dependency

 Task 1 and Task 2 must start at the same time.



Benefit of using SS Dependency
Overlapping work helps to reduce the overall duration of a project. In our Testing Project, as we can see from the Total Duration of the Project, we Save 3 days’ work by using SS Dependency.


C. Finish - to  - Finish Dependency

Task 1 and Task 2 must finish at the same time.

FF dependencies also reduce the overall amount of time in Project, same as SS Dependency.
  • If Task 1 will take 5 days to complete, and Task 2 will take 3 days to complete, with FS dependency the overall duration of the two tasks is 8 days.
  • If  we set an FF dependency, the overall duration of the two tasks is only 5 days.

D. Start - to  - Finish Dependency

Task 2 cannot finish until the start of Task 1.  This is VERY RARE scenario of Task in any type of Project.


As we can see Task 2 has been moved from his scheduled Start date due to SF Relationship. 

As an Example,  A particular task needs to finish before a milestone or project finish date, but it doesn't matter exactly when and we don't want a finish  it late to affect the regular task in that scenario we can use SF dependency

18 comments:

  1. It's very useful . Think peacefully :)

    ReplyDelete
  2. Useful comprehensive and useful.

    ReplyDelete
  3. If task 1 has successor mentioned as ( task2SS+10days). What does it mean

    ReplyDelete
  4. When task 1 has successor mentioned as task2SS+ 10 days . What does it mean ?

    ReplyDelete
    Replies
    1. It means task2 has to start 10 days after the star of task1

      Delete
  5. +10 means it has to way to wait for 10 days before it start

    ReplyDelete
  6. This is very useful.
    Also the comments below, have been useful.
    Thanks much!

    ReplyDelete
  7. nice post! I really like and appreciate your work, thank you for sharing such a useful information about project management, keep updating the information, hear i prefer some more information about jobs for your career hr jobs in hyderabad .

    ReplyDelete
  8. Kindly told me whats mean
    2FS-6Days

    ReplyDelete
  9. Really well information. Thanks a lot. Here, I got the special deals for Microsoft Project Professional and many more .Our specialty is quick email delivery. You will get 24/7 support. So let’s check it out.

    ReplyDelete