Task Dependencies : To Define the Relationships Between Tasks
Predecessor :
A predecessor is a task whose start or finish
date determines the start or finish date of its successor task.
Successor :
A successor is a task whose start or finish date
is driven by its predecessor task.
The nature of the relationship between a
predecessor task and a successor task determines the type of task dependency to
use. We can use FOUR types of task dependencies.
- Finish - To - Start [ FS ]
- Start - To - Start [ SS ]
- Finish - To - Finish [ FF ]
- Start - To - Finish [ SF ]
For Example, if we have Two tasks, Task 1 and Task 2 in our Testing Project , we can define all the 4 relationships by following steps:
- If Task 2 is having Predecessor as Task 1, double Click on Task 2
- Task Information window will appear
- In the Predecessor section, select the option from Type Drop down list ( FS / SS / FF / SF)
- Ok
A. Finish - to - Start Dependency
Task
1 must finish before Task 2 can start. This is the By Default Dependency created and very commonly used Relationship in Project.
B. Start - to - Start Dependency
Task
1 and Task 2 must start at the same time.
Benefit of using SS Dependency
Overlapping work helps to reduce the overall duration of a project.
In our Testing Project, as we can see from the Total Duration of the Project, we Save 3 days’ work by using
SS Dependency.
C. Finish - to - Finish Dependency
Task
1 and Task 2 must finish at the same time.
FF
dependencies also reduce the overall amount of time in Project, same as SS Dependency.
- If Task 1 will take 5 days to complete, and Task 2 will take 3 days to complete, with FS dependency the overall duration of the two tasks is 8 days.
- If we set an FF dependency, the overall duration of the two tasks is only 5 days.
D. Start - to - Finish Dependency
Task
2 cannot finish until the start of Task 1. This is VERY RARE scenario of Task in any type of Project.
As we can see Task 2 has been moved from his scheduled Start date due to SF Relationship.
As an Example, A particular task needs to finish
before a milestone or project finish date, but it doesn't matter exactly when
and we don't want a finish it late to affect the regular task in that scenario we can
use SF dependency
It's very useful . Think peacefully :)
ReplyDeleteTQ guys
ReplyDeleteYes chandan it is very good topic
ReplyDeleteThank you for the kind word sir..
DeleteUseful comprehensive and useful.
ReplyDeleteThank you for your feedback !!
DeleteIf task 1 has successor mentioned as ( task2SS+10days). What does it mean
ReplyDeleteWhen task 1 has successor mentioned as task2SS+ 10 days . What does it mean ?
ReplyDeleteIt means task2 has to start 10 days after the star of task1
Delete+10 means it has to way to wait for 10 days before it start
ReplyDeleteThis is very useful.
ReplyDeleteAlso the comments below, have been useful.
Thanks much!
Thank you for your feedback !!
DeleteThank you, very helpful
ReplyDeleteThank you for your feedback !!
Deletenice post! I really like and appreciate your work, thank you for sharing such a useful information about project management, keep updating the information, hear i prefer some more information about jobs for your career hr jobs in hyderabad .
ReplyDeleteKindly told me whats mean
ReplyDelete2FS-6Days
2FS+6days means?
ReplyDeleteReally well information. Thanks a lot. Here, I got the special deals for Microsoft Project Professional and many more .Our specialty is quick email delivery. You will get 24/7 support. So let’s check it out.
ReplyDelete