Task Dependencies : To Define the Relationships Between Tasks
Predecessor :
A predecessor is a task whose start or finish
date determines the start or finish date of its successor task.
Successor :
A successor is a task whose start or finish date
is driven by its predecessor task.
The nature of the relationship between a
predecessor task and a successor task determines the type of task dependency to
use. We can use FOUR types of task dependencies.
- Finish - To - Start [ FS ]
- Start - To - Start [ SS ]
- Finish - To - Finish [ FF ]
- Start - To - Finish [ SF ]
For
Example, if we have Two tasks, Task 1 and Task 2 in our Testing Project
, we can define all the 4 relationships by following steps:
- If Task 2 is having Predecessor as Task 1, double Click on Task 2
- Task Information window will appear
- In the Predecessor section, select the option from Type Drop down list ( FS / SS / FF / SF)
- Ok
A. Finish - to - Start Dependency
Task
1 must finish before Task 2 can start. This is the By Default Dependency created and very commonly used Relationship in Project.
B. Start - to - Start Dependency
Task
1 and Task 2 must start at the same time.
Benefit of using SS Dependency
Overlapping work helps to reduce the overall duration of a project.
In our Testing Project, as we can see from the Total Duration of the Project, we Save 3 days’ work by using
SS Dependency.
C. Finish - to - Finish Dependency
Task
1 and Task 2 must finish at the same time.
FF
dependencies also reduce the overall amount of time in Project, same as SS Dependency.
- If Task 1 will take 5 days to complete, and Task 2 will take 3 days to complete, with FS dependency the overall duration of the two tasks is 8 days.
- If we set an FF dependency, the overall duration of the two tasks is only 5 days.
D. Start - to - Finish Dependency
Task
2 cannot finish until the start of Task 1. This is VERY RARE scenario of Task in any type of Project.
As we can see Task 2 has been moved from his scheduled Start date due to SF Relationship.
As an Example, A particular task needs to finish
before a milestone or project finish date, but it doesn't matter exactly when
and we don't want a finish it late to affect the regular task in that scenario we can
use SF dependency
nice post! I really like and appreciate your work, thank you for sharing such a useful information about project management, keep updating the information, hear i prefer some more information about jobs for your career hr jobs in hyderabad .
ReplyDeleteThanks for the information. Very useful...god bless
ReplyDeleteThanks... Very clearly defined... Quite easy to understand... Many thanks...
ReplyDeleteI recently completed this course at ExcelR. I found this course very demanding. I learned a lot in this course. I was particularly impressed with the trainers which is the best feature of ExcelR. There is a wide breadth of topics covered in a short period of time. Love ExcelR.
ReplyDeleteMicrosoft Project Training In Hyderbad
This information is impressive; I am inspired by your post writing style & how continuously you describe this topic. After reading your post, thanks for taking the time to discuss this, I feel happy about it and I love learning more about this topic.
ReplyDeleteprimavera training in chennai
Many thanks for resourceful information
ReplyDelete
ReplyDeleteThanks for sharing such an amazing information its very beneficial for our company. our company name is innomatics research labs we offering data science,big data and many more courses to make student career success full and we are giving online, classroom and corporate training our website is https://www.innomatics.in
I like viewing web sites which comprehend the price of delivering the excellent usefulPython classes in puneresource free of charge. I truly adored Python classes in pune reading your posting. Thank you!
ReplyDeleteReally well information. Thanks a lot. Here, I got the special deals for Microsoft Project Professional and many more .Our specialty is quick email delivery. You will get 24/7 support. So let’s check it out.
ReplyDeleteThank you for your explanation. It helps me a lot to understand better now.
ReplyDeleteThis is not correct. A finish-to-finish dependency between tasks 1 and 2 does not force tasks 1 and 2 to finish on the same date, and a start-to-start dependency does not force tasks 1 and 2 to start on the same date.
ReplyDeleteSee the following definitions of FF and SS dependencies, which were taken directly from a Microsoft support page
https://support.microsoft.com/en-us/office/link-tasks-in-a-project-31b918ce-4b71-475c-9d6b-0ee501b4be57
Finish-to-Finish (FF)
The dependent task (B) cannot be completed until the task that it depends on (A) is completed.
The dependent task can be completed at any time after the task that it depends on is completed. The FF link type does not require that both tasks be completed at the same time.
For example, if you have two tasks, "Add wiring" and "Inspect electrical," the "Inspect electrical" task cannot be completed until the "Add wiring" task is completed.
Start-to-Start (SS)
The dependent task (B) cannot begin until the task that it depends on (A) begins.
The dependent task can start at any time after the task that it depends on begins. The SS link type does not require that both tasks begin at the same time.
For example, if you have two tasks, "Pour concrete" and "Level concrete," the "Level concrete" task cannot begin until the "Pour concrete" task begins.
This is not correct. A finish-to-finish dependency between tasks 1 and 2 does not force tasks 1 and 2 to finish on the same date, and a start-to-start dependency does not force tasks 1 and 2 to start on the same date.
ReplyDeleteSee the following definitions of FF and SS dependencies, which were taken directly from a Microsoft support page
https://support.microsoft.com/en-us/office/link-tasks-in-a-project-31b918ce-4b71-475c-9d6b-0ee501b4be57
Finish-to-Finish (FF)
The dependent task (B) cannot be completed until the task that it depends on (A) is completed.
The dependent task can be completed at any time after the task that it depends on is completed. The FF link type does not require that both tasks be completed at the same time.
For example, if you have two tasks, "Add wiring" and "Inspect electrical," the "Inspect electrical" task cannot be completed until the "Add wiring" task is completed.
Start-to-Start (SS)
The dependent task (B) cannot begin until the task that it depends on (A) begins.
The dependent task can start at any time after the task that it depends on begins. The SS link type does not require that both tasks begin at the same time.
For example, if you have two tasks, "Pour concrete" and "Level concrete," the "Level concrete" task cannot begin until the "Pour concrete" task begins.